    Hello! Thanks for the replies.

    By cupboard it’s actually a dimmer/patch room in which we’re putting a ventilated wall Mounted rack with cooling and air handling. We’re installing rf distribution room and monitoring for the wireless microphones will be through network manager on an iPad. The rack with the desk in will house a projection switcher but we want to keep the weight down in that rack as it will have to be carried down the tiered seating when it is being folded up.

    So would we be correct that we could use an AR168 on stage and an AR84 in the patch room and have the capability to patch any of the 24 inputs to any channel on the desk? The unit on stage will likely be disconnected a lot of the time when it isn’t needed and we will have the facility to patch the AR84 directly into the desk, when we do this will we need to repatch? Can this be recalled as part of a show/scene so we can do all the patching and tell the users just to recall the correct scene based on if the two stage boxes are in use or just one?

    Also another question! The distance between the AR168 and AR84, will this be able to be a 100m along with the 100m between the desk and the AR168?

    Thanks again!